* SHVL-012/2000, 0GB | * SHVL-012/2000, 0GB | ||
* Started a bit late due to restart of Hb system, first several scans recorded on HOB+0124/3200, first allegedly good scan 050-1837 (Liza) | * Started a bit late due to restart of Hb system, first several scans recorded on HOB+0124/3200, first allegedly good scan 050-1837 (Liza) | ||
+ | * 11:25UT: Scan 051-1119c has the last 4 minutes waiting at the elevation limit - the source may not be properly within the beam (Chris) | ||
+ | * 15:00 UT: Contacted Michael onsite to restart the D-Link router as all connections to Yg had been severed. Connections re-established at 15:35 UT.(vk) | ||