* 00:49UT - FS terminated due to operator error, restart delayed due to drive PC crash. Schedule resumed with first good data from 0103. (JMc) | * 00:49UT - FS terminated due to operator error, restart delayed due to drive PC crash. Schedule resumed with first good data from 0103. (JMc) | ||
* Missed scans 010-0049 and 010-0056 (JMc) | * Missed scans 010-0049 and 010-0056 (JMc) | ||
+ | * 06:05UT - S/X receiver pressure rising, Warren is heading out to fix the He pressure which is also falling and will fix this also. However, he can't go out until after his lecture. Data from now until otherwise said will be subject to higher than nominal system temperatures. (Tiege) | ||
**Katherine** | **Katherine** |