CRF101

Hobart 26m

Module HOB+0094/16000, start 5993.29 GB

  • 1730UT Experiment started OK (JS)
  • 1750UT through 2220UT Getting consistent tsys overflows in vd, ve, i2, i3. unsure if this is an issue as tsys measurements are ok as are power levels (JS)

Hobart 12m

Module HOB+1007/16000, start 10226.56 GB

  • 1730UT Experiment started OK (JS)
  • 1932UT (and 2220UT) ongoing errors
    ERROR s5 -112 rfpcn: EOF pre-draining input, rfpic probably crashed, connection closed

    likely unsolvable without hardware replacement according to Jamie (JS)

Katherine 12m

Module HOB+0119/160000, start 0.0 GB

  • 1730UT Experiment started OK (JS)