User Tools

Site Tools


handover:r4690

This wiki is not maintained! Do not use this when setting up AuScope experiments!

This is an old revision of the document!


R4690

Hobart

Module: BKG+0136, 1.0 GB

Katherine

Module: NAIC-004, 1.0 GB

  • Maser AHM power ~/= on 23.8 (blue number). Should call Brett during the day (Lucia)
  • 02:31:06 UT PPS Delay through DBBC changed. This may cause a small break in the clock offset (Imogen)

Yarragadee

Module: USN-0087, 1.0 GB

  • ifc on 63 attenuation but the power levels look good (Lucia)
You could leave a comment if you were logged in.
/home/www/auscope/opswiki/data/attic/handover/r4690.1433471818.txt.gz · Last modified: 2015/06/05 02:36 by Jim Lovell